ExcerptsRevenue GenerationL&T pointed out that the project helped vehicles save fuel and vehicle operating costs due to reduction of distance by 2.5 km and free flow traffic, besides time. ChallengesL&T faced problems with the tolling of the old Athupalam bridge, which did not come within the route of the bypass. This bridge was an already existing facility being used by the incoming traffic from Kerala to Tamilnadu.
|